News
-
Equipment Advisory: Unit 1 offline for maintenance
Read More: Equipment Advisory: Unit 1 offline for maintenanceUnit 1 at the Holyrood Thermal Plant has been taken offline to complete some planned maintenance. The unit will be returned to service on November 10th. There is no impact to our customers as a result of this work. Customers can follow us at twitter.com/nlhydro and facebook.com/nlhydro for any critical customer information.
-
Equipment Advisory: Holyrood combustion turbine removed from service for maintenance
Read More: Equipment Advisory: Holyrood combustion turbine removed from service for maintenanceNewfoundland and Labrador Hydro (Hydro) is advising customers that the combustion turbine at the Holyrood plant has been removed from service to complete maintenance work, and is expected to return to service tomorrow evening (November 7, 2017). There is no anticipated customer impact at this time. This advisory is part of Hydro’s ongoing commitment to keep customers…
-
Equipment Advisory: Transmission line from Upper Salmon to Bay d’Espoir out for maintenance Nov. 2nd
Read More: Equipment Advisory: Transmission line from Upper Salmon to Bay d’Espoir out for maintenance Nov. 2ndNewfoundland and Labrador Hydro (Hydro) advises that the transmission line from Upper Salmon to Bay d’Espoir is out of service November 2, 2017 for planned maintenance. There are no anticipated customer impacts as a result of this work. This equipment advisory is part of Hydro’s commitment to keep customers informed on the status of the electricity system.
-
Notice for residents of Holyrood – emissions issue occurred Saturday, October 28
Read More: Notice for residents of Holyrood – emissions issue occurred Saturday, October 28On Saturday, October 28 an oxygen sensor on one of the boilers at the Holyrood Plant malfunctioned for period of time (about 90 minutes) and therefore some unburned fuel particles in the form of soot and smoke – were expelled from the stack. Hydro is committed to protecting the environment and over the years we have made…
-
Equipment Advisory: Transmission Line from Bay d’Espoir to Sunnyside out of service
Read More: Equipment Advisory: Transmission Line from Bay d’Espoir to Sunnyside out of serviceNewfoundland and Labrador Hydro (Hydro) advises that one of the transmission lines from Bay d’Espoir to Sunnyside will be out of service October 31, 2017 to facilitate planned maintenance at the Bay d’Espoir facility. There are no anticipated customer impacts as a result of this work. This equipment advisory is part of Hydro’s commitment to keep customers informed…
-
Update (Oct. 30th) – Equipment Advisory: Transmission line to Avalon Peninsula out of service for extended period during connection to new switchyard at Soldiers Pond
Read More: Update (Oct. 30th) – Equipment Advisory: Transmission line to Avalon Peninsula out of service for extended period during connection to new switchyard at Soldiers PondUpdate: October 30, 2017 – This work is complete and the transmission lines have been returned to service. Previous Advisory: October 6, 2017 – Newfoundland and Labrador Hydro (Hydro) is advising that one of the main transmission lines to the Avalon Peninsula will be out of service from October 6 to mid-November. The transmission line,…
-
Outage Advisory: Emergency Outage for Baie Verte Peninsula today
Read More: Outage Advisory: Emergency Outage for Baie Verte Peninsula todayHydro is advising customers on the Baie Verte Peninsula of a planned outage today in order for emergency repairs to be made to a damaged Newfoundland Power transmission line. The outage will be from approximately 1:00 to 4:00 p.m. today (Oct. 25) and will affect communities on the Baie Verte Peninsula, including : Brent’s Cove Burlington Baie…
-
Spill Advisory: Upper Salmon in Central Newfoundland
Read More: Spill Advisory: Upper Salmon in Central NewfoundlandNewfoundland and Labrador Hydro is advising residents, cabin owners and travellers in the Upper Salmon area of Central Newfoundland that the Company will be releasing water at its North Salmon Dam Spillway into the North Salmon River for a brief period of time on October 26 for the purpose of testing new equipment on the…
-
Equipment Advisory: Maintenance on transmission line from Bay d’Espoir to Stony Brook
Read More: Equipment Advisory: Maintenance on transmission line from Bay d’Espoir to Stony BrookHydro advises that the Bay d’Espoir to Stony Brook transmission line will be out of service October 24-25 for planned maintenance. There are no customer impacts anticipated.
-
Advisory: Upper Lake Melville Work Re-scheduled for this Weekend
Read More: Advisory: Upper Lake Melville Work Re-scheduled for this WeekendAdvisory: Upper Lake Melville Work Re-scheduled for this Weekend Back up generation is available, but we’re asking customers to conserve where possible We would like to advise our customers that the previously postponed equipment outage for the Upper Lake Melville area has been rescheduled for this weekend: Saturday, Oct. 14 beginning at 10:00 p.m.…