Public Advisory: Testing To Continue This Week On the Labrador Island Link

UPDATE: April 8th, 11:00am

The second 700 MW high power pole trip test of the Labrador Island Link is complete. The system performed as expected without any customer outages. Power flows will stay at 675MW and be monitored for the next 12 hours as part of these ongoing tests.

Although early in our analysis, we are pleased with how the Labrador Island Link performed during these tests. This last phase of testing was an important step toward final commissioning of this asset. Thank you for your continued patience—We know you are counting on us to provide safe, reliable energy, and we take that responsibility seriously.

We will have more information in the coming days and weeks.

——-

UPDATE: April 6th, 2:15pm

We have now completed the first of two 700 MW pole trip tests on the Labrador Island Link. The system performed as expected without any customer outages. Power flows will stay at 675MW and be monitored for the next 12 hours as part of these ongoing tests.

Thank you for your continued patience as we move towards our final test this Saturday, April 8th.

——-

UPDATE: April 5th, 2pm

Tomorrow morning, we will be proceeding with high power tests at 700 MW, beginning at approximately 10:30am. Although we do not expect disruption to service, there is an increased risk of a brief outage during testing activities. We are prepared and have available supply to bring customers back online quickly if needed.

The second 700 MW test is tentatively planned for Saturday, April 8.

We appreciate your patience as we move through these tests this week.

——-

UPDATE: April 2nd, 4:15pm

We have now completed the 500 MW high power tests on both poles of the Labrador Island Link with no issue or customer impact.

Although early in our analysis, we are pleased with how the Labrador Island Link performed during these tests. This last phase of testing is an important step toward final commissioning of this asset. Thank you for your continued patience as we move towards our final tests later this week. We know you are counting on us to provide safe, reliable energy, and we take that responsibility seriously.

——-

UPDATE: April 1st, 6:00pm

Testing activities have concluded for the day. Calibration tests on Pole 2, up to 675 MW were completed today without issue or customer impact.

Tomorrow morning, we plan to proceed with high power tests at 500 MW. Although we do not expect disruption to service, there is an increased risk of a brief outage during testing activities. We are prepared and have available supply to bring customers back online quickly if needed.

The first of the 700 MW tests is tentatively planned for April 6 and the second for April 8.

We appreciate your patience as we move through these tests.

——-

UPDATE: March 31st, 6:00pm

Testing activities for today have now concluded.

We have completed all calibration tests on Pole 1, up to 675 MW. The tests were completed without issue or customer impact. We have updated the schedule based on progress to date. We will begin the same series of calibrations tests on Pole 2 starting 8:30 tomorrow morning, expected to conclude by 6:30pm.

Again, while we do not expect disruption to service, there is an increased risk of a brief outage during testing activities. We are prepared and have available supply to bring customers back online quickly if needed.

The high power tests at 500 MW are now tentatively planned for Sunday, April 2. The first of the 700 MW tests is tentatively planned for April 6, and the second now moved to April 8.

We appreciate your patience as we move through these tests.

——-

UPDATE: March 30th, 5:20pm

Testing activities have concluded for the day. We appreciate your patience as we move through this phase of testing. Calibration testing will resume tomorrow, March 31 at 8:30am and is expected to continue until 6:30pm.

——-

Newfoundland and Labrador Hydro is continuing to test the Labrador-Island Link this week.

We will be moving through a series of tests beginning March 30th, 2023. We’ll be monitoring the system closely during testing and will keep customers informed on the status of the system if issues arise. Updates will be added to this page, as well as to Facebook and Twitter.

Calibration Tests will be conducted over two days, March 30 and 31, between 8:30am – 6:30pm daily. Following successful completion of these tests, we will move into high power tests at 500 MW on April 1 and 700MW on April 2 and 6, tentatively.

During testing, there is a risk of a customer impact. If there is a power interruption, we are prepared and have supply available to restore customers quickly (typically under 30 minutes).

Running the Labrador-Island Link at higher power levels is an important step toward final commissioning of this asset. We appreciate your patience as we move through this next phase of testing. As we work to strengthen our electricity system, we know you are counting on us to provide safe, reliable energy and we take that responsibility seriously.

The Labrador-Island Link is the transmission line bringing power from the completed Muskrat Falls facility in Labrador to the Soldier’s Pond terminal station on the island.

What is Underfrequency Load Shedding?


https://my.nlhydro.com/outage/