Equipment Advisory – Holyrood Unit 1
March 12th, 2017
Update March 12 – Holyrood Unit 1 was successfully restored to service at approximately 5PM on Sunday evening.
Newfoundland and Labrador Hydro is advising that Unit 1 at the Holyrood Thermal Generating Station is offline. The unit tripped offline when a St. John’s transmission line tripped due to the extreme wind and weather conditions being experienced in the province.
There is no customer impact as a result of this unit being offline. Updates will be provided through our website and social media channels.
Media Contact:
Jill Pitcher
Senior Communications Advisor, Newfoundland and Labrador Hydro
t. 709.737.1219 / c. 709.689.9938 e. [email protected]