Equipment Advisory (UPDATED) – Holyrood Units and CT
Update
All generation units at the Holyrood plant (Units 1, 2, 3 and the combustion turbine) are available for service.
Update December 15
Unit 2 has been taken offline until December 17 to complete an additional piece of work. Units 1 and 3 and the combustion turbine are available.
Update Dec 13
Unit 1 has been returned to service as scheduled. Units 2 and 3 and the combustion turbine are also available for service.
Update Dec 11
Advising that Unit 1 will be offline for two days for final maintenance completion. Units 2 and 3 and the combustion turbine are also available for service.
———————-
Nov 26 – Newfoundland and Labrador Hydro (Hydro) is advising that Unit 2 at the Holyrood Thermal Generating Station has been taken offline today for additional maintenance. It will be offline for a period of 2 days.
Units 1 and 3 are online and available to the system
Hydro has sufficient generation reserves and there is no customer impact from this equipment outage.
Hydro’s equipment maintenance is a critical part of ensuring the delivery of safe, reliable electricity service to customers. All planned system outages are evaluated to eliminate or minimize potential customer impacts.
Any changes to the status of the electricity system and or any significant system events will be communicated to customers.
For more information follow Hydro at www.Twitter.com/NLHydro, www.Facebook.com/NLHydro or visit www.nlhydro.com.